The death of twenty four students owing to a sudden surge in the Beas at Thalout by the release of waters from the Larji Dam yesterday is another instance of how the hydel projects in Himachal just don't give a damn about safety-whether it is of the environment or of human beings. And this time the HP govt. can't just wash its hands off the whole matter because the Larji Project is its own, and is operated by the HPSEB.
The HP govt. has for years been warned of the heavy price that it is paying-and will continue to pay-for the reckless stupidity and cupidity with which it has been devastating its river and mountain systems. The environmental degradation in all its four major riverine valleys has been well documented and has reached a point of no return. Local villagers from Kinnaur to Bharmour have for years been protesting against the threats that these projects hold out to their lands and lives. NGOs, social activists and nature lovers of all shades have been petitioning the govt. and the courts to stop this wanton destruction. But the politicians and bureaucrats ensconced in Ellerslie can count only the megawatts and hear only the ringing of the cash registers.
That was bad enough, but as the tragedy at Larji demonstrates, these hydel projects have also severely compromised human safety in order to cut costs and make even more money. It is an internationally mandated and accepted practice that all dams and reservoirs are required to install warning systems- advance proclamations, sirens, flashing lights-that have to be activated BEFORE releasing any unusual quantity of water. Shockingly, this is not insisted upon in Himachal. Similar accidents have happened in this state in the past also, in the sutlej by the release of waters from the Nathpa-Jhakri project, in the Ravi valley and elsewhere, and lives have been lost before though not on the colossal scale as this time. But the Larji is a govt. project and the HP govt. and its HPSEB cannot hide from the question- why did it not issue an alarm before releasing the waters, and did it even have an advance warning system in place? I am given to understand that HPSEB had been repeatedly advised by environmental and safety experts to install these systems but it took a conscious decision NOT TO DO SO BECAUSE IT FELT THAT IT WAS AN UNNECESSARY COST! If this is true-and this aspect needs to be thoroughly investigated-it was an unpardonable, and a criminal, error of judgement and all those who were a party to it must be proceeded against. The ire of the local villagers after the incident, who blocked traffic to protest against the callousness of the project authorities, lends credence to the suspicion that no alarm system existed, or even if it did, it was never activated. They have complained of similar flash releases in the past. This just begs the question- how many megawatts is a human life worth, in the estimation of our project administrators?
An immediate safety audit of ALL the hydel projects in the state must be carried out because with the monsoons approaching more such sudden releases from dams will become necessary.
The Larji project is also responsible for another piece of engineering which is another disaster in waiting- the Larji Traffic Tunnel on the national highway between Mandi and Kullu. This 3.50 kilometer tunnel was constructed by the project as an alternative because the original stretch of the highway was submerged by the Larji reservoir. There are no checkposts at either ends of the tunnel and not a single telephone inside as an emergency instrument which could be used in case of an accident. If any accident happens inside the tunnel-car crash, tunnel collapse, landslide-those inside have no means of contacting anyone for help. ( There is no cell phone connectivity within the tunnel). Once again, it needs to be reiterated that all global practices stipulate that such long tunnels should compulsorily have such communication systems, but Larji again appears to have cut corners. This also needs to be rectified immediately.
The Himachal govt., whose undertaking is the prime mover of this tragedy, cannot be entrusted with an inquiry into this incident. Furthermore, this is not an isolated incident and the larger issue of safety/ warning systems in ALL hydel projects in the state needs to be investigated properly. It is therefore only proper that the govt. constitute a judicial commission to enquire into the matter and all its related aspects.
The HP govt. has for years been warned of the heavy price that it is paying-and will continue to pay-for the reckless stupidity and cupidity with which it has been devastating its river and mountain systems. The environmental degradation in all its four major riverine valleys has been well documented and has reached a point of no return. Local villagers from Kinnaur to Bharmour have for years been protesting against the threats that these projects hold out to their lands and lives. NGOs, social activists and nature lovers of all shades have been petitioning the govt. and the courts to stop this wanton destruction. But the politicians and bureaucrats ensconced in Ellerslie can count only the megawatts and hear only the ringing of the cash registers.
That was bad enough, but as the tragedy at Larji demonstrates, these hydel projects have also severely compromised human safety in order to cut costs and make even more money. It is an internationally mandated and accepted practice that all dams and reservoirs are required to install warning systems- advance proclamations, sirens, flashing lights-that have to be activated BEFORE releasing any unusual quantity of water. Shockingly, this is not insisted upon in Himachal. Similar accidents have happened in this state in the past also, in the sutlej by the release of waters from the Nathpa-Jhakri project, in the Ravi valley and elsewhere, and lives have been lost before though not on the colossal scale as this time. But the Larji is a govt. project and the HP govt. and its HPSEB cannot hide from the question- why did it not issue an alarm before releasing the waters, and did it even have an advance warning system in place? I am given to understand that HPSEB had been repeatedly advised by environmental and safety experts to install these systems but it took a conscious decision NOT TO DO SO BECAUSE IT FELT THAT IT WAS AN UNNECESSARY COST! If this is true-and this aspect needs to be thoroughly investigated-it was an unpardonable, and a criminal, error of judgement and all those who were a party to it must be proceeded against. The ire of the local villagers after the incident, who blocked traffic to protest against the callousness of the project authorities, lends credence to the suspicion that no alarm system existed, or even if it did, it was never activated. They have complained of similar flash releases in the past. This just begs the question- how many megawatts is a human life worth, in the estimation of our project administrators?
An immediate safety audit of ALL the hydel projects in the state must be carried out because with the monsoons approaching more such sudden releases from dams will become necessary.
The Larji project is also responsible for another piece of engineering which is another disaster in waiting- the Larji Traffic Tunnel on the national highway between Mandi and Kullu. This 3.50 kilometer tunnel was constructed by the project as an alternative because the original stretch of the highway was submerged by the Larji reservoir. There are no checkposts at either ends of the tunnel and not a single telephone inside as an emergency instrument which could be used in case of an accident. If any accident happens inside the tunnel-car crash, tunnel collapse, landslide-those inside have no means of contacting anyone for help. ( There is no cell phone connectivity within the tunnel). Once again, it needs to be reiterated that all global practices stipulate that such long tunnels should compulsorily have such communication systems, but Larji again appears to have cut corners. This also needs to be rectified immediately.
The Himachal govt., whose undertaking is the prime mover of this tragedy, cannot be entrusted with an inquiry into this incident. Furthermore, this is not an isolated incident and the larger issue of safety/ warning systems in ALL hydel projects in the state needs to be investigated properly. It is therefore only proper that the govt. constitute a judicial commission to enquire into the matter and all its related aspects.
This preventable loss of young lives is so tragic and the way to make it not entirely in vain is to force enough safeguards for the future. As you say a judicial commission will be the most likely to uncover facts and make impartial recommendations in regard to all such projects. Thanks for highlighting this, and the long tunnels without communications as another potential disaster.